Log In

View Full Version : Roadwork in downtown Sebastopol



Barry
07-09-2010, 03:01 PM
Caltrans Highway 12 Resurfacing Schedule - Downtown Sebastopol

All work to be performed between 9 p.m. and 6 a.m.
No daytime road closures.

Wednesday July 7 Remove striping and pavement markers
Monday,Tuesday July 12,13 Misc prep work and grinding
Wednesday-Friday July 14-16 Repairs, crack seal, install signal loops
Saturday-Monday July 17-19 Asphalt paving
Thurs-Fri, Monday July 22,23,26 New striping and pavement markers